Type: Elevated
Freeway
Date: 1996–1997
Location: Oahu, Hawaii
General Contractor: Kiewit Pacific
Length of Bridge: 5,105 ft. (2 miles, including east- and westbound)
|
Products:
260 haunch girders
270 drop-in girders |
Click below to view products:
|
|

H3 Freeway on the Kaneohe side of Oahu. |

Erection of the precast haunch girder. |
|
 |
Additional information
This project was a redesign, from C.I.P. bents and precast
drop-in girders to a fully precast segmental bridge utilizing bulb-tee
girders.
The span was 200 feet. Haunch girders varied in size from 6
feet 6 inches deep to 9 feet. over the bents and 80 feet long.
Drop-in girders were 6 feet 6 inches deep by 120 feet long.
|
 |