Studies > Cache Creek Casino |
 |
Type: Parking
Structure
Date: April 2003
Location: Brooks, California
General Contractor: HMH Construction
Stories: Five
Parking stalls: 1,883
Size: Approx. 130,000 sq. ft.
Erection Time/Schedule: Five
weeks
|
Products:
484 precast beams and girders
162 precast columns |
Click below to view products:
|
|

Interior columns and standard Hawaiian I beams. |

Exterior moment frame columns of the hybrid frame. |

Post-tensioned cast-in-place deck slab and the precast frame. |

Exterior view of the moment frame columns and moment frame cast-in-place
beams. |
|
 |
Additional information
Con-Fab employed a “hybrid scheme” that utilized
precast beams and columns with 5-inch post-tensioned deck slabs.
The lateral loads on the structure (seismic and wind) were taken
by perimeter moment frames using full height moment frame columns and
C.I.P. upturned moment frame beams.
|
 |